Support #3587

closed

sidup mati listrik sebagian

Added by Arko Sasongko 7 months ago. Updated 7 months ago.

Status:
Closed
Priority:
Normal
Assignee:
Start date:
10/09/2024
Due date:
% Done:

100%

Estimated time:
Spent time:
Platform:
User:
SP:
Sprint:
Actions #1

Updated by Arko Sasongko 7 months ago

  • Status changed from New to In Progress
  • % Done changed from 0 to 50

- sidup mati listrik sebagian;
- mati listrik sebagian lt.2, termasuk ruang server;
- mati listrik lt.3;

Actions #2

Updated by Arko Sasongko 7 months ago

- listrik nyala kembali;
- hidupkan server2 di ruang server lt.2;
- problem dengan server 22, tidak mau up, cek problem;

Actions #3

Updated by Arko Sasongko 7 months ago

- server 22 sudah up kembali;
- ada hdd yang problem, hdd diganti dengan hdd lain;

Actions #4

Updated by Arko Sasongko 7 months ago

  • Status changed from In Progress to Closed
  • % Done changed from 50 to 100